Xpress Georgia


FAST SCHEDULES

Future Xpress Routes and Park & Ride Lots

The 2003 Xpress operations plan calls for implementing more than 37 routes by the year 2010. At present, the Georgia Regional Transportation Authority (GRTA) and its partner county governments have 15 routes in operation. GRTA implements new routes as new coaches arrive and park & ride lots become available either through construction or lease agreements. The Georgia Department of Transportation is responsible for constructing park & ride lots for Xpress operations. Here is the status of new routes planned in the next year and of park & ride lots:

Route 400 Cumming

Description: This Forsyth County route is operating from a temporary lot on Castleberry Road in Cumming and serves North Springs, Perimeter Center and downtown Atlanta.
Location: A new lot is under construction in the western corner of the intersection of GA 400 and GA 20. Click here for photo.
Status: Construction bids in July 2006
Projected to Open: Fall 2007

Route 422 Panola Road
Route 428 Panola Road

Description: New routes operating from South DeKalb County. Route 422 will serve downtown Atlanta. Route 428 will serve Doraville and Perimeter Center areas.
Location: The southwest corner of the intersection of I-20 and Panola Road. Click here for photo.
Status: Construction under way.
Projected to Open: Spring 2007

Route 432 Stockbridge

Description: New Henry County route to serve downtown Atlanta.
Location: In the northeast corner of the intersection of I-75 and GA 138 (Stockbridge Road). Click here for photo.
Status: In final design stage. Construction bids will be let in October 2006
Projected to Open: Fall 2007

Route 442 Riverdale

Description: New Clayton County route to downtown Atlanta.
Location: East side of Lamar Hutcheson Parkway between Valley Hill Rd. and Roberts Dr. Click here for photo.
Status: Bids to be let in October 2006
Projected to Open: Fall 2007

Route 470 Hiram-Powder Springs

Description: Route operated by Cobb Community Transit from Hiram and Powder Springs to downtown Atlanta.
Location:  New Cobb County lot will be constructed east of Florence Road and south of Sailors Parkway diagonally across from the current Silver Comet trailhead parking lot. Click here for photo.
Status: Construction bids to be let in October 2006.
Projected to Open: Summer 2007

Home |  About Xpress |  Accessibility |  Contact Xpress |  Customer Service |  Xpress It |  Xpress Schedules |  Xpress Tickets  
System Map |  Partner Systems  |  Customer Bill of Rights |  Lost and Found |  GRTA Home |  Privacy Policy |  Employment

©2004, 2005 GRTA
This website requires Microsoft Internet Explorer 4 or Netscape version 4 as well as screen resolution of at least 800x600.
Contact the webmaster  if you experience any technical problems.